REQUIREMENTS:
  • Separation plant for an open area of 53 hectares
  • Short time schedule for project implementation
  • Permanent availability of the separation system for continuous operation while refuelling aircraft
  • Low maintenance costs
  • Reliability
  • Maintenance-free filter technology
  • Prevents oil leakage during flooding

SOLUTION:
1st CONSTRUCTION PHASE:
Large separation plant in compact design

  • 18 sludge traps 5,000 l in round design with PEHD inliners
  • 18 high-performance SYSTEM H-C2 NS80 l/sec separators with PEHD inliner (synthetic inside lining)
  • Flood-proof oil storage tank
  • It is possible to clean and partially drain the system while it is in operation
  • Monitoring system with connection to control centre
  • Stainless steel manhole covers with gas struts

2nd CONSTRUCTION PHASE:
Large separator system in existing concrete basin

  • 10 Stainless steel SYSTEM H NS 60 l/sec modules
  • Flood-proof oil reservoir and oil extraction connections
  • Warning system with connection to control centre